8/15/2026

Article 37: Workshop foundations

Workshop foundations

The last two days have been intense. Following the excavation in July, we have started digging the trench for the workshop foundation, under the terrace. Most of the work is done with shovels and wheelbarrows. Thanks to everyone who came to help, including the youngest, Mathis and Olivia.

At the same time, work is continuing inside. The electrics are being installed and the technical room is gradually filling up. The electrician and Jérôme have started connecting the photovoltaic solar panels; a few connections still remain. We have also started the interior painting.