7/11/2026

Article 36: Excavation under the terrace

Excavation under the terrace

Work has resumed outside with the preparation of the terrace. We have decided to build a workshop underneath it. To get the necessary headroom, we need to dig about 60 cm into the ground.

This week, we therefore spent three days with a digger to carry out this excavation. By lowering the ground level, we have created a small embankment that will need to be retained. The next steps will be the foundations, the drainage and the retaining wall.