1/18/2026
Article 30: Kitchen, shower and technical room
Since the beginning of the year, we have been making slow but steady progress on the interior installations.
The kitchen is taking shape with a special feature: it will reveal the straw behind the worktops, protected simply by a pane of glass. The technical room is equipped: the walls are covered with OSB and Fermacell to mount all the electrics for the solar panels. The shower took precision work: it took two people a whole day to recess three battens and the electrical conduits directly into the straw wall.