3/17/2025

Article 16: Technical installation under way

Technical installation under way

Early March sees the site start up again after the February break. We begin with the electrical conduits, laying out the routes for the house’s electrical system. The conduits will allow the wires to be pulled through properly once the structure is in place.

At the same time, the first major deliveries are arriving: 7 cubic metres of sand for the interior plasters and the 32 solar panels that will supply our electricity.